K Street Bridge Replacement Show Details

Location
Martin, Tennessee
Completion Date
2009
Description

  • Design Team:

  • Terry Drumwright, P.E.
  • Robert Jowers, P.E.
  • Sam Snider
  • Jerry McMullin

  • Project Details:

TLM Associates, Inc. was retained to provide planning, hydraulic analysis, environmental permitting, design, construction administration, construction observation, and close out services for this project funded in part by a grant from the Tennessee Department of Transportation.

To preserve the natural stream channel, maintain the current roadway elevation, and facilitate rapid construction, TLM Associates selected a 42-foot-wide pre-manufactured concrete arch bridge to span the channel and provide the hydraulic capacity needed to replace an aging three span bridge. This bridge provided an aesthetically pleasing solution in an urban setting in lieu of standard concrete box culverts and span type bridges.